CLARKSTON - Due to inclement weather, the paving in the City of Clarkston originally scheduled for June 29 and 30 has been rescheduled for July 6 and 7.

As part of the City of Clarkston 2020 Street Maintenance Project, the following are dates and locations of street and alley paving activities. The areas will be signed for “No Parking” for the day of scheduled work. We ask residents along these streets to refrain from parking in the street and move any RV’s trailers, or boats from the street. Please call Kevin Poole, Public Works Director if you have any questions. The Contractor, Poe Asphalt Paving, Inc. will have traffic control flaggers and measures in place at each paving location.

July 6 schedule of streets and alleys:

  • 6th St. Bridge to Fair (east half)
  • Alley 6th - 7th Bridge to Fair
  • Alley 6th - 7th Poplar to Bridge
  • Alley 6th - 7th Maple to Poplar
  • Alley 8th to 9th Bridge to Fair
  • 9th St. Poplar to Maple (east half)
  • 9th St. Maple to Elm (east half)
  • Alley 10th – 11th Maple to Poplar

July 7 schedule of streets:

  • 6th St. Bridge to Fair (west half)
  • 9th St. Poplar to Maple (west half)
  • 9th St. Maple to Elm (west half)
  • Waste Water Treatment Plant
  • 9th St. Highland Ave. to 10th St.
  • 10th St. 10th to 9th